DHAKA, 12 December 2022, (TON): As part of pre-commission, flushing of systems with the open reactor has commenced at unit-1 of Rooppur Nuclear Power Plant.

According to a message received, chemically dematerialized water is supplied to the reactor vessel through the connection pipeline and primary circuit pipelines to remove impurities left after the installation of the equipment and the pipelines at this stage.

Alexey Deriy, Vice President of ASE and Director of RNPP Construction Project said "flushing of active and passive safety systems with the open reactor is one of the most important pre-commissioning operations. This is the first of a whole series of inspections of equipment and process systems.”